Mary Callahan, THE PRESS DEMOCRAT
Overlooking water that was swiftly running through a broad channel that was mostly a patch of thick brush and trees until last year, local and federal officials and others on Monday marked the halfway point in a 13-year, $81 million fish habitat restoration project along Dry Creek.
In the past seven years, Sonoma Water and the U.S. Army Corps of Engineers have completed about 3 of the 6 miles of streambed they intend to rehabilitate and enhance to give endangered salmonid species that call the creek home a better chance to survive.
“This is, I think, one of the gems of our region and really a highlight project,” Army Corps Brigadier General Kimberly Colloton told those assembled.
As they toasted the conclusion of the final phase in the first round of projects at the edge of a Ferrari-Carano vineyard in Healdsburg, the two key partners approved an agreement committing to continued work on the effort.
But they have little choice. A 2008 biological opinion issued by the National Marine Fisheries Service required the two agencies to restore 6 out of 14 miles of Dry Creek. The work had to be done if they were to continue operating the Warm Springs Dam at Lake Sonoma for flood control and water deliveries to 600,000 consumers throughout Sonoma and northern Marin counties.
The order came in response to findings that water releases made since completion of the dam in 1984 were often at too high a velocity for juvenile fish to rest or feed adequately. Moreover, such fast-moving water further scoured and straightened out the streambed, exacerbating the problem.
The work they’ve been doing since is designed to spread the creek out, creating side- and cross-channels and dead-ended alcoves that slow the water down to a stop. They’ve added giant root wads, boulders, tree stumps and other woody debris to create places for small fish to hide and rest, and put in willows and other plants on the banks for shade.
Read more at https://www.pressdemocrat.com/news/9516210-181/work-to-continue-on-second