PG&E plans to remove both Potter Valley Project Dams—Mendo, Humboldt, Lake and Sonoma Fight

Sarah Reith, REDHEADED BLACKBELT

A planning group for the Russian River Water Forum, which is preparing for life after PG&E decommissions the Potter Valley Project, met for the first time yesterday in Ukiah. PG&E said in a town hall last month that its version of decommissioning means removing both dams. That’s unless an entity that is capable of running them steps forward before it submits a draft of the decommissioning plan to the Federal Energy Regulatory Commission, or FERC.

Tony Gigliotti, PG&E’s senior licensing project manager, laid out the timeline at a town hall about Scott Dam and Lake Pillsbury on April 27th.

“When we say decommissioning in this case, both dams will be removed as part of that, unless somebody comes forward with a proposal that PG&E looks at and accepts,” he said. “We need to ensure they can operate the dams after we give up ownership. In terms of timelines for the surrender application, there will be an initial draft November, 2023. A second draft, also available for public review, May 2024, and then the final application will be filed with FERC in January, 2025.”

Janet Walther, PG&E’s senior manager of hydro licensing, qualified that timeline a little.

“When PG&E submits our final surrender application to FERC, that would be the point of no return,” in terms of decommissioning, she said. “And really, the draft. We are looking to know, sooner than later, if there’s an entity interested in taking over the dam because that will change our surrender application and what we put in that surrender application. So I think we are looking and would like to see some initial proposals later this year, if there is interest. And we are talking with folks, as we have been since 2016, about potential interest in future ownership of Scott, and/or Cape Horn Dam.”

Read more at https://kymkemp.com/2023/05/18/pge-plans-to-remove-both-potter-valley-project-dams-mendo-humboldt-lake-and-sonoma-fight/

Posted on Categories Water, WildlifeTags , , , , , , , , ,

Russian River flows at risk: New studies show potential path forward for Potter Valley project

Mother of All Groups (MOAG), SONOMA COUNTY GAZETTE

PG&E’s license to operate the Potter Valley Project expires in April of 2022. For more information until then: http://pottervalleyproject.org/

A group of studies released last month paint a clearer picture of how Sonoma and Mendocino counties can meet future water needs while reducing environmental impacts in the face of a decision by PG&E to cease operation of an aging hydroelectric power project.

The Potter Valley Project (PVP) is located approximately 15 miles north of the City of Ukiah on the Eel River. The Project’s facilities include two dams, a diversion tunnel and a hydroelectric plant located in Potter Valley in the headwaters of the Russian River. The 100-year-old project produces little electricity by modern standards and is a net money loser, but Sonoma and Mendocino County water users have grown accustomed to the water diverted by the Project which flows from the Eel River into the Russian River watershed where it is stored in Lake Mendocino – ultimately flowing down the Russian River where it benefits agricultural interests and residents.

This arrangement was put in jeopardy when PG&E announced in 2019 that it would not seek to renew its federal license to operate the Project, which expires in April 2022. In recent weeks, PG&E also notified the public that the Project’s powerhouse had suffered a transformer failure, which eliminated its ability to generate electricity and reduced water diversions into the Russian River. Given PG&E’s goal to dispense with the Project, it is unlikely the powerhouse will be repaired or that the Project will ever function as it once did.

In response to PG&E’s decision to divest from the Project, a diverse group of stakeholders called the Two-Basin Partnership was formed to develop a plan to take over and modify the Project in a way that reflects regional needs and priorities in both basins. Among these priorities are fisheries recovery in the Eel River – one of the few major rivers left in California that has the potential to support abundant, self-sustaining wild populations of salmon and steelhead – and water supply reliability for Russian River water users. The Partnership’s proposed plan included the removal of Scott Dam, restoration of the drained Lake Pillsbury footprint and modifications or the replacement of Cape Horn Dam to maintain a diversion.

Read more at https://www.sonomacountygazette.com/sonoma-county-news/russian-river-flows-at-risk-new-studies-show-potential-path-forward-for-po/

Posted on Categories WaterTags , , , , ,

Local coalition advances plan to remove Scott Dam on the Eel River, acquire Potter Valley Project from PG&E

Ryan Burns, LOST COAST OUPOST

n a major development for both water rights and the environment on the North Coast, an unlikely coalition of five regional entities today filed a plan with the Federal Energy Regulatory Commission (FERC) to take over the Potter Valley Project, a hydroelectric facility that diverts water from the Eel River.

For Humboldt County residents in particular, the plan is significant because it calls for the removal of Scott Dam, a 98-year old hydroelectric wall that has had major detrimental impacts to native migratory fish populations, including salmon and steelhead.

The five entities in the coalition known as the Two-Basin Partnership include the County of Humboldt, the Mendocino County Inland Water & Power Commission, the Round Valley Indian Tribes, California Trout and the Sonoma County Water Agency.

These groups have distinct and sometimes conflicting objectives for the water that’s at stake, with environmental interests clamoring for fisheries restoration while agricultural users in the Potter Valley and water agencies in the Russian River basin have their own uses in mind. Agricultural interests in the Potter Valley and upper Russian River basin want the water to irrigate their crops, primarily vineyards. Sonoma and Mendocino water agencies want it to supply their customers and meet their contract obligations.

“The glue that has held this two-basin solution together is that everybody has a heck of a lot to risk here,” Congressman Jared Huffman told the Outpost this morning. “Nobody has a slam dunk on what they want.”
Continue reading “Local coalition advances plan to remove Scott Dam on the Eel River, acquire Potter Valley Project from PG&E”

Posted on Categories Agriculture/Food System, Habitats, Water, WildlifeTags , , , , , , ,

Scott Dam slated for removal in plan by Sonoma County and partners to control hydropower project

Guy Kovner, THE PRESS DEMOCRAT

Enviro Updates: From the Eel River Action Plan 2016, by California Trout: “The Eel River is the third largest river entirely in California.The Eel River ecosystem, its salmon and steelhead populations, and other native fish and wildlife populations have been in decline for the past century and a half. It has been transformed from one of the most productive river ecosystems along the Pacific Coast to a degraded river with heavily impaired salmonid populations.”

A nearly century-old dam on the Eel River that impounds Lake Pillsbury is slated for removal under a $500 million proposal helmed by Sonoma County and four other regional partners seeking to take over from PG&E a remote but pivotal hydropower project in Mendocino County.

The coalition, including Mendocino and Humboldt counties, hailed the proposal as a milestone in their effort to meet the needs of all three counties, protecting water supplies for farmers, fish and communities, including a key source of supplemental water for the Russian River system that serves 600,000  customers in Sonoma and Marin counties.

The dam removal alone, a long-sought goal of environmental groups and fish advocates, would be the highest-profile project to improve habitat for imperiled North Coast salmon and steelhead in decades, perhaps behind only the dam removals planned on the Klamath River within the next two years.

“The good news is that Scott Dam is coming out,” said Scott Greacen, conservation director for Friends of the Eel River, a nonprofit that for decades has been pursuing removal to open up more than 300 miles of spawning habitat in the upper Eel. Due mainly to dams, water diversion and other development, the river’s salmon and steelhead “have paid a devastating price, going from a million fish a year to the brink of extinction,” he said.

The proposal, submitted Wednesday to federal officials, has also stirred passions among those dismayed by the prospective loss of a 2,300-acre recreational lake deep in the Lake County portion of Mendocino National Forest. Santa Rosa residents George and Carol Cinquini, who have held a cabin at Lake Pillsbury since the 1940s, are annoyed that the 450 homeowners, ranchers and small business owners in the lake community were excluded from the planning process.

“We tried to get our foot in the door,” said Carol Cinquini, vice president of the Lake Pillsbury Alliance, which was formed last year.

“We’re very upset,” said George Cinquini, an alliance board member. The reservoir, about two hours from Santa Rosa is a haven for water sports, and without it, Cinquini warned, Russian River flows will be diminished in dry years.

But North Coast Rep. Jared Huffman, D-San Rafael, who brought local shareholders together to chart the project’s future, said the proposal is the only way to guarantee a “really important water resource” for the Russian River.

The 98-year-old dam has long outlived its purpose, he said, and the coalition project, dubbed the Two-Basin Partnership, calls for habitat restoration “to rejuvenate one of our great salmon rivers in California.”

State Sen. Mike McGuire, D-Healdsburg, whose district stretches across both drainages, called for Lake County to be added to the partnership because Lake Pillsbury and most of the Eel River’s headwaters are in the county.

Read more at https://www.pressdemocrat.com/news/10960029-181/sonoma-county-backs-plan-to

Posted on Categories WaterTags , , , , , , ,

CalTrout wants old Scott Dam on Eel River removed to help salmon and steelhead

Guy Kovner, THE PRESS DEMOCRAT

A state environmental group is calling for the removal of an old dam on the Eel River, contending it threatens the future of protected salmon and steelhead while acknowledging it is a key part of the North Bay’s water supply.

Scott Dam, a 138-foot concrete dam erected in 1922, is one of five aging dams California Trout asserts are “ripe for removal” to benefit their natural surroundings and communities.

The nearly 50-year-old nonprofit known as CalTrout said in its report, “Top 5 California Dams Out,” the Eel River represents “perhaps the greatest opportunity in California to restore a watershed to its former abundance of wild salmonids.”

Scott Dam, located in Lake County’s portion of the Mendocino National Forest, has been a longstanding target of other groups, including Friends of the Eel River, who want steelhead, coho and chinook salmon to swim freely within the 288 miles of habitat in the Eel watershed blocked by the dam.

The environmentalists see a “unique opportunity” to achieve their goal, as California’s largest utility PG&E, which has owned the dam as part of a small hydropower project since 1930, has filed Chapter 11 bankruptcy and abandoned plans to sell or seek relicensing of the project that diverts 20 billion gallons of water a year from the Eel to the Russian River at Potter Valley.

Eel River interests have considered the diversion a form of theft, while the water is critical to towns and ranches on the upper Russian River from Potter Valley to Healdsburg and part of the water supply for 600,000 residents in Sonoma and Marin counties.

How the future of the Potter Valley Project will play out over the next 18 months to two years is unclear, but it appears likely to result in either decommissioning or relicensing of the project, which includes a small powerhouse and two Eel River dams.

The bottom line is either PG&E or a new owner of the project may face a choice between paying more than $90 million for a fish ladder at Scott Dam or about $70 million to remove it.

Read more at https://www.pressdemocrat.com/news/9312399-181/state-environmental-group-wants-old